Tiffany Construction Company

General Construction Projects

Thousand Trails Site Expansion –    

Compleition Date: May 2019

Contracting Entity: Equity Lifestyles

We were contracted to construct 62 new RV sites at Thousand Trails RV Park for their park expansion. This included the relocation and installation of approximately 4000 lf of new sewer mainline and services, 4000 lf of electrical conduit and approximately 100 lf of new water main line and services.

 

Chavez Ranch Road –    

Compleition Date: April 2018

Contracting Entity: Chavez Ranch Road Construction Corporation

Project consists of constructing 1.2 miles of new roadway to Yavapai County Specifications including 42,300 cy of earthwork, 2642 tons of asphalt, 6807 lf of curb & gutter, 2024 lf of guardrail, MSE retaining walls, multiple box culverts and slope stabilization, 930 lf of stormdrain ranging in size from 18” to 54”

 

Rio De Flag Restoration Improvement JOC  

Compleition Date: May 2017

Contracting Entity: Coconino County

TCC was awarded this project by Coconino County as part of the effort to reclaim and restore a section of the Rio De Flag natural water channel from previous industrial use. In conjunction with Coconino County and the City of Flagstaff, we are also extending the Flagstaff Unified Trail System (FUTS) through the project and adding viewshed berms and an enhanced trailhead while preserving existing archeological sites. The project entailed extensive and intricate grading of slopes and viewshed berms, setting large boulders to replicate existing rock outcroppings, erosion control including rock check dams and rip rap, pulverizing 5,550 sy of existing 10” thick asphalt, placement of 2380 sy of 4” asphalt, placement of 800 sf of 8” concrete pad, 2230 lf of fencing and gates, relocation of reclaimed water line and new valve house, drainage piping and extensive irrigation including trees and shrubs. We completed this project on budget and ahead of schedule.

Intel - CH 8   

Compleition Date: 2/2014

Contracting Entity: M&W Group

This project entailed all underground mainline and services for sewer, domestic water, gas and firelines including tie-ins to existing facilities for the new CH-8 building at Intel’s Chandler Campus. We also installed storm drain, drainage structures, detention basins, and grading and paving of all roadways and parking lots.

 

L’Auberge De Sedona –    

Compleition Date: 1/15/2009

Contracting Entity: L’Auberge-Orchards, LLC

L’Auberge was one of our most complicated projects to date. We were tasked with managing and coordinating the construction and redesign of one of Sedona’s premier resorts while the resort remained open. This project utilized and tested the skills of our project managers and foremen. Working closely with Shephard-Westnitzer’s design team, our project manager directed our crews in rock excavation, utility installation and site construction for 36 pre-manufactured cabins added to the existing resort including 19 cabins placed on the hillside, supported by caissons as well as a two level, 150 stall parking garage while coordinating with over a dozen subcontractors who were working simultaneously.

The unique challenges encountered here included:
  • Maintaining a safe environment for the resort staff and quests
  • Managing a multiple activities in an extremely small area
  • Safely excavating a nearly vertical rock hillside for construction of a parking garage and new units
  • Addressing the daily environmental protection of Oak Creek
  • Working with multiple local and state agencies and utilities
  • Readjusting the schedule and approach to allow for design changes and alterations
We successfully faced each challenge while maintaining satisfaction with subcontractors, agencies and the client.

 

APS - Casner Wilderness Access Road Construction

Compleition Date: 2011

Contracting Entity: Arizona Public Service

Tiffany worked with APS and the US Forest Service to improve an access road through eight miles of “Protected Wilderness” on Casner Mountain, which provided access to APS’s 750 KVA Highlines. We worked closely with the Forest service to protect the area’s environment and minimize impact while meeting the Client’s needs. During this project we encountered two feet of snow cover and faced many challenges of safely mobilizing crews and equipment to a remote site. The client was extremely pleased with the expedience and quality of the work performed and the manner in which it was accomplished.
 

Sedona Uptown Enhancement CMAR   

Compleition Date: 2007

Contracting Entity: City of Sedona

Working with the design engineer and the City of Sedona, we were able to trim over a million dollars from the original budgeted amount. This was a complex project regarding construction and scheduling as the project was completed while the many retail shops, restaurants and hotels remained open during peak season. Our work included asphalt paving of Hwy 89A, intricate demolition, decorative concrete sidewalks (redesigned to be ADA compliant), retaining walls, utility relocations (including coordination with various utility providers), installation of new utilities and storm drain. The project was completed on schedule and within budget, receiving numerous commendations from the City of Sedona and the merchants for our diligence, professionalism and our responsiveness to resolving potential issues.